The grant closeout checklist

Everything final is due 120 days after the period of performance ends — reports, liquidation, refunds. The checklist, and the two deadlines that catch people out.

LAST REVIEWED 28 AUGUST 2026

Closeout is the part of the grant lifecycle that arrives after everyone has stopped paying attention. The programme is over, the staff who ran it have moved on to the next award, and the deadline that matters most is the one nobody is watching. It is also where a clean grant turns into an audit finding, because the rules that govern it are specific, time-boxed, and easy to miss once the work itself is done.

This is what federal closeout actually requires under the Uniform Guidance, the two deadlines that catch people out, and the obligations that keep running long after the award is closed.

The 120-day clock

The governing rule is 2 CFR 200.344. It gives the recipient a single, hard deadline: you must submit all reports the award requires — financial, performance and any others — no later than 120 calendar days after the conclusion of the period of performance. Not the end of your fiscal year, not the anniversary of the award: 120 days from the day the period of performance ends.

That clock starts whether or not anyone reminds you. The award document sets the end date; the 120 days run from it automatically. The single most common closeout failure is not a bad report, it is a late one, filed by a person who assumed the date was later than it was because the file had been closed in everyone’s head months earlier.

What closeout actually requires

“Close the grant” is not one task. It is a short checklist of distinct obligations, most of them also bounded by that same 120-day window:

  • Submit all final reports. The final financial report (commonly an SF-425), the final performance report, and anything else the terms name — each to its correct recipient and portal.
  • Liquidate all financial obligations. 200.344 requires you to liquidate every financial obligation incurred under the award no later than 120 days after the period of performance ends. Liquidate means settle and pay, not merely record.
  • Draw down or refund correctly. Make any final drawdown for costs already incurred, and promptly refund any unobligated cash the agency or pass-through entity advanced that you are not authorised to keep.
  • Account for property and equipment. Equipment and supplies bought with federal funds carry disposition rules that can outlast the award (2 CFR 200.313, 200.314). Closeout is when you confirm what you hold and whether the funder needs disposition instructions.
  • Close out your subrecipients first. If you passed funds through, your 120-day clock depends on theirs. A subrecipient that reports on day 119 leaves you no time, so their closeout has to be scheduled to land well before yours.

The two clocks people miss

The period of performance is not the spending deadline. It is the window in which you may incur obligations — do the work, place the orders. Once it ends you cannot incur new costs, but you still have the 120 days to liquidate what you already incurred. Reading the end of performance as “the day the money must be spent” is what produces a scramble of last-week purchases that are then hard to defend as allowable.

The agency has a clock too. Under 200.344 the Federal agency must make every effort to complete all closeout actions no later than one year after the end of the period of performance. That year is not a grace period for you — your 120 days still stand — but it explains why an award can still generate correspondence, and adjustments, months after you filed your final report.

After closeout: what does not end

Closing an award does not close the file. Two obligations continue, and both are routine audit checks precisely because organisations assume they stopped.

Records must be kept for three years. Under 2 CFR 200.334 financial records, supporting documents and statistical records must be retained for three years from the date you submit the final financial report — not three years from the award start, which is the version people tend to remember. Equipment records run three years past final disposition, which can be later still.

Post-closeout adjustments can still happen. A closed award can be reopened for a disallowed cost or an audit finding, and amounts can still be recovered. Closeout ends your reporting obligations; it does not end your accountability for what the money did.

This is the case Grantwell is built for: the end-of-performance date comes straight off the award, the 120-day closeout obligations are generated from it and counted down with the rest of the calendar, and the retention clock is set from the day the final report is actually filed — so the award that everyone stopped watching is the one still being watched.

This guide is general information about how grant compliance work is commonly organised, not legal, audit or accounting advice. Grant rules change, and terms vary by funder and award — always check your own award documents and the current regulation, and talk to your auditor about your specific circumstances.

Primary sources

This guide is general information about how grant compliance work is commonly organised, not legal, audit or accounting advice. Grant rules change, and terms vary by funder and award — always check your own award documents and the current regulation, and talk to your auditor about your specific circumstances.